Karimnagar/Hyderabad, June 7 (Hydnow): Irrigation Minister Uttam Kumar Reddy has ordered the construction companies to speed up the repair work in the affected areas of the Kaleshwaram project.
After the end of the election code. Annaram, Medigadda and Sundilla barrages were inspected. On this occasion, the Minister said, “Due to the Election Code, there was no review on Kaleswaram.
“Medigadda Shriveled during the Indian rule. If the project built after borrowing Rs. 94 thousand crores collapses, the current Congress government will have to pay interest on it.
When the Congress came to power, we asked the National Dam Safety Authority to look into it. The expert committee made some suggestions.
It was concluded that if the gates had been lifted as soon as the Madigadda collapsed, such damage would not have happened.
She said that the gates of the three barrages of Annaram, Medigadda and Sundilla should be lifted after doing some repairs at the damaged places. Came to inspect the works. Work is progressing rapidly at Medigadda and Annaram.
As the Sundilla barrage work is progressing slowly, we have been asked to speed it up. We have ordered the construction companies to complete the work before the rains. We will build a dam at Tummadihatti, said Uttam. (Hydnow)
Next Story:
-
No Change In Gold Prices In Hyderabad Today

The gold rates today stable in Hyderabad on 19 April, 2026. Going by the rates today, the price of 10 grams of 22-carat gold is Rs. 1,42,800 while the rate of 10 grams of 24-carat gold is at Rs 1,55,780.
Now you can get the latest stories from Hydnow every day. Click the link to subscribe. Click to follow Hydnow’s Facebook page and Twitter and Instagram